Projektledelse og forundersøgelse - Mikkels Spørgsmål - 2024

Spørgsmål udarbejdet fra materiale


Click the button to start the quiz

Start Quiz

<- Leave quiz



Questions in the quiz (21)


What is a project?

Acording to PMI (Project Management Institute)

  • An established objective

  • A defined live span with a beginning and an end

  • Usually, the involvement of several departments and professionals

  • Typically, doing something that has never been done before

  • Specific time, cost, and performance requirements

What is correct about a program

  • A program is a group of related projects

What is the four typical phases of a project?

  • Defining

  • Planning

  • Execution

  • Closure

What is usually included in the project definition phase?

  • Goals

  • Specifications

  • Tasks

  • Responsibilities

What is usually included in the project planning phase?

  • Schedules

  • Budgets

  • Resources

  • Risks

  • Staffing

What is usually included in the project execution phase?

  • Status reports

  • Changes

  • Quality

  • Forecasts

What is usually included in the project closure phase?

  • Train customers

  • Transfer documents

  • Release resources

  • Evaluation

  • Lessons learned

What does a Project Manager do?

  • Plan

  • Schedule

  • Motivate

  • Control

  • Direct link to customer

  • Provide direction

  • Coordination

  • Integration to the project team

What are some of the current drivers of project management?

  • Compression of the Project Life Cycle

  • Knowledge Explosion

  • Triple Bottom Line

  • Increased Customer Focus

  • Small Projects Represent Big Problems

What is EV?

  • Earned Value

What does EV show?

  • The value of the work, in terms of the budgeted cost, that has been accomplished

What is PV?

  • Planned Value

What does PV show?

  • The value of the work planned to be accomplished

What is AC?

  • Actual Cost

What does AC show?

  • The actual cost incurred for the work accomplished

What is BAC?

  • Budget cost at Completion

What is EAC?

  • Estimated cost at Completion

What is ETC?

  • Estimated cost to complete remaining work

What is VAC?

  • Cost variance at Completion

What is SV?

  • Schedule Variance

What is CV?

  • Cost Variance